Polaris was a 105-acre mass grading site package that consisted of approximately 550,000 CY of mass grading and associated storm drain, topsoil respread, and seeding. The package also included around 96,500 SY of base stone on the building pad, laydown area, and haul road. The project had a strict completion schedule for the building pad and laydown area — half of which was contracted to be completed by May 15, 2015, with the remainder of the building pad to be completed by June 15, 2015. Despite the heavy spring rains, the project was completed on schedule.

Project Gallery

  • Type of WorkSite preparation
  • LocationMadison, Alabama
  • OwnerPolaris Industries
  • Key Factors

    Very strict deadline for completion

  • End ResultDespite heavy spring rains, the project was completed on time